WO-2026-0421
Investigate P-202 pump seal — CH4 alarm
P1DispatchedScope of work
Replace mechanical seal on P-202 crude transfer pump. Three LEL events in 30d traced to suction-side seal weep.
Work instructions
Step-by-step procedure per equipment type
- 1Issue isolation permit
- 2LOTO motor MCC-04 and block valves
- 3Drain pump to closed system
- 4Pull seal cartridge
- 5Install new seal per OEM IOM 5.3
- 6Re-torque to 75 ft-lb star pattern
- 7Reinstate, function test
- 8Bump-test SGA-1043
HSE procedures
Permits & PPE required for this work
- LOTO suction/discharge/motor
- Confined space permit
- 4-gas monitor
- Hot-work NOT permitted until LEL <10%
Activity timeline
4 events · most recent first
DW
- Status → Dispatched2026-06-28 10:54by Dana WhitfieldScheduled 2026-06-28 12:30
- Assigned to Luis Ortega2026-06-28 10:50by Dana WhitfieldMechanical crew
- Work order created2026-06-28 10:42by ForesightSource: Alert
- Alert triggered2026-06-28 10:39by ForesightAuto-linked to this work order
Details
Asset
P-202
Area
Area 1 / Tank Farm
Craft
Mechanical
Assigned
Luis Ortega
Scheduled
2026-06-28 12:30
Est. hours
4h
Source
Alert
Created
2026-06-28 10:42
Actions
Update status, priority, or log a work note
Status
Priority
Assign to