WO-2026-0415
Quarterly LDAR sweep — Tank Farm A
PMVerifiedScope of work
EPA Method 21 Leak Detection And Repair sweep.
Work instructions
Step-by-step procedure per equipment type
- 1Survey flange/valve components
- 2Tag leakers >500 ppm
- 3Issue follow-up WOs
HSE procedures
Permits & PPE required for this work
- LEL monitor
- Hot-work prohibited
Activity timeline
8 events · most recent first
DW
- Status → Verified2026-06-15 14:30by Dana WhitfieldPost-work bump test passed
- Status → Completed2026-06-15 14:00by Dana WhitfieldActual 6.0h
- Progress note2026-06-15 09:30by Dana WhitfieldExecuted steps 1–5 per procedure. As-found readings recorded.
- Status → In Progress2026-06-15 08:52by Dana Whitfield
- On-site note2026-06-15 08:45by Dana WhitfieldArrived at Area 1 / Tank Farm. Isolation permit issued, area clear.
- Status → Dispatched2026-06-15 08:12by Dana WhitfieldScheduled 2026-06-18 09:00
- Assigned to Dana Whitfield2026-06-15 08:08by Dana WhitfieldOperations crew
- Work order created2026-06-15 08:00by ForesightSource: PM Schedule
Details
Asset
T-101/T-102
Area
Area 1 / Tank Farm
Craft
Operations
Assigned
Dana Whitfield
Scheduled
2026-06-18 09:00
Est. hours
6h
Source
PM Schedule
Created
2026-06-15 08:00
Actions
Update status, priority, or log a work note
Status
Priority
Assign to